Bill of quantities¶
Naksha measures brickwork, plaster, paint, flooring, the slab, columns, steel, doors and windows from your plan, prices them at your rates in ₹, and adds up the total. You can save the bill as a CSV file or draw it on the drawing as a table.
Type BOQ (or ESTIMATE), or go to Tools ▸ Bill of Quantities….
What Naksha needs on the plan¶
The bill is measured from what's drawn in model space. Each item needs something on the plan to measure.
| On the plan | How you draw it | What it gives |
|---|---|---|
| Rooms | ROOM, counted as Carpet |
Flooring, internal plaster, paint |
| Balconies | ROOM, counted as Balcony / terrace |
Balcony flooring |
| The floor's outer outline | ROOM, counted as Built-up |
Slab, external plaster |
| Brick walls | HATCH inside the walls with the AR-BRSTD pattern, or any hatch on a layer with WALL in its name |
Brick masonry |
| Doors, windows, ventilators, columns | Placed from the Blocks tab (Tools ▸ Tool Palettes (Blocks), or Ctrl+3) | Doors, windows, RCC columns |
| Reinforcement | The bar bending schedule (BBS) |
Steel and binding wire |
Rooms and area statements shows how to mark rooms and the built-up outline with ROOM. Blocks, libraries and references covers the Blocks tab, and Bar bending schedule and beam detail covers the steel.
Making the bill¶
- Type
BOQ, or go to Tools ▸ Bill of Quantities…. -
Fill in the boxes at the top:
Box What it's for Starts at Title A name for the bill, such as Row house, BanerEmpty Wall height (m) Height of the walls, for brickwork, plaster, paint and columns 3 Slab (mm) Thickness of the RCC slab 125 Door height (m) What a doorway takes out of brickwork and plaster 2.1 Window height (m) Window area is width × this height 1.2 Contingencies % Added to the total in a second total row 0 Floors Floors like this plan 1, or the Floors set in Steel from plan -
Naksha lists each item with its Unit, Quantity, Rate (₹) and Amount (₹), and the Total at the bottom.
- Click a rate and type your own. The amount and total change when you leave the box or press Enter.
- If you typed contingencies, a second row shows Total with 5% contingencies (for 5%).
- Click Export CSV to save the bill as a file, or Place on drawing to draw it as a table. Close closes the box.

If nothing on the plan can be measured, the box says so and lists what to draw.
What the bill lists¶
| Item | Unit | How Naksha measures it |
|---|---|---|
| Brick masonry 230 mm in CM 1:6 | m³ | Hatched wall area × wall height, less the door and window openings × 0.23 m |
| RCC M20 columns, one line for each size | m³ | Number of columns × their size × wall height |
| RCC M20 slab | m³ | Built-up area × slab thickness |
| Steel reinforcement, TMT (grade): cut, bent and placed | kg | The bar bending schedule's total, with its wastage |
| Binding wire, 18 gauge | kg | 8 kg for each tonne of steel |
| Internal plaster 12 mm CM 1:4 | m² | Room perimeters × wall height, less openings |
| External plaster 20 mm CM 1:4 | m² | Built-up outline × wall height, less openings in the outer walls |
| Interior emulsion paint, 2 coats | m² | The same area as internal plaster |
| Vitrified tile flooring 600 × 600 | m² | Carpet area |
| Anti-skid tile flooring (balconies) | m² | Balcony area |
| Flush door with frame and fittings, one line for each width | nos | Door blocks counted |
| Aluminium sliding window or ventilator, one line for each width | m² | Number × width × height (a ventilator is taken as 0.45 m high) |
The steel grade is the one chosen in the bar bending schedule, Fe 500D unless you change it.
An item with nothing to measure is left out of the bill. Hover over a description to see exactly how it was worked out, such as carpet area 66.76 m².
Openings¶
Door and window openings are taken out of brickwork, plaster and paint. Their width comes from the block's name, such as KZ-DOOR-900 or KZ-WIN-1500, so use the doors and windows from the Blocks tab.
- Brickwork loses each opening's area × the wall's 230 mm thickness.
- An opening in an inside wall comes off the internal plaster on both faces.
- An opening within a wall's thickness of the built-up outline is in an outer wall. It comes off the internal plaster on one face and the external plaster on the other.
Floors¶
Floors multiplies everything measured on the plan. If the plan is a typical floor of a G+2 building, type 3. The description's hover text then ends in × 3 floors.
Steel and binding wire aren't multiplied, because the bar bending schedule already covers the whole building.
Rates¶
Every rate starts at a sample figure, marked sample, so you can see a rough total straight away. Type your project's rates over them.
| Item | Sample rate |
|---|---|
| Brick masonry | ₹ 7,500 a m³ |
| RCC slab | ₹ 11,000 a m³ |
| RCC columns | ₹ 12,000 a m³ |
| Steel | ₹ 75 a kg |
| Binding wire | ₹ 90 a kg |
| Internal plaster | ₹ 450 a m² |
| External plaster | ₹ 550 a m² |
| Paint | ₹ 180 a m² |
| Vitrified flooring | ₹ 1,600 a m² |
| Balcony flooring | ₹ 1,400 a m² |
| Doors | ₹ 16,000 each |
| Windows | ₹ 9,000 a m² |
One rate covers all the lines of a kind. All the doors share the door rate, and all the windows and ventilators share the window rate.
Naksha remembers the rates and the boxes at the top for your next bill. Click Sample rates to go back to the samples.
Note
Your rates are kept on this computer, not inside the drawing file. Someone else opening the drawing sees their own rates.
Saving the bill as a CSV file¶
Export CSV saves a file named after the title (or the drawing, if there's no title), ending in -boq.csv, such as Row_house_Baner-boq.csv.
The file has the heading BILL OF QUANTITIES – (title), then the columns No., Description, Unit, Quantity, Rate (₹), Amount (₹) and How measured, then the total rows. It's saved in UTF-8, so ₹ and m² come through. Open it in Ganit to add your own items or turn it into a quotation.
In the CSV file the amounts are plain numbers, without lakh commas.
Placing the bill on the drawing¶
- Click Place on drawing. The box closes and the table follows the cursor.
- Naksha asks
Specify insertion point or [Scale/Rotate]:. Click to put the table down.
The table is a block named KZ-BOQ-1 (then KZ-BOQ-2 and so on), headed BILL OF QUANTITIES – (title). The amounts are written with lakh commas, like 12,34,567.00, and the total rows in capitals.

- On the drawing, the rate and amount columns are headed Rate (Rs) and Amount (Rs).
- The table is sized for the drawing's scale. For a 1:100 drawing, set Overall scale to 100 in Format ▸ Dimension Style… first. On a layout, it's at sheet size.
- The table doesn't change when the plan or the rates change. Erase it and place it again.
Good to know¶
- Quantities are always in metric units (m³, m², kg, nos), even in a feet-and-inches drawing. Rates are per m³, m², kg or each.
- Slab and external plaster need the Built-up outline. Without it, those two lines don't appear.
- One wall height is used for the whole bill.
- The bill is an estimate from the drawing. It has no lines for excavation, footing concrete, plumbing or electrical work. Add those to the CSV file yourself.